Hyundai Transys

TMED-II — plant line installation

Over one hundred machines received, rigged, set, connected and commissioned across the plant's production lines — inside a facility that was already running.

Client
Hyundai Transys
Location
Monterrey, Nuevo León
Services
Rigging & machine moving, Utilities, Industrial electrical, Automation & controls

The work

TMED-II is a full plant installation: not a single line, but every production line in the facility, built out machine by machine while the plant kept operating.

Equipment arrived from Korea by sea container on a schedule we did not control, which meant the site had to absorb whatever landed that week and keep moving. Our crews off-loaded and uncrated every container on site, moved each machine to its position with our own heavy forklifts, and set it on foundation to the builder's levelling tolerance. Because the plant was in production, heavy moves were planned around live traffic and running lines rather than the other way around.

With the machines set, we ran and terminated the utilities: 480 V power, compressed air, process water and coolant. Every connection point was recorded and validated against the layout, so hand-over came with a documented list rather than a walk-through.

The lines were handed over connected, dry-run and ready for production.

Scope

  • Container off-loading and uncrating on site
  • Heavy rigging and in-plant transport with owned 15 t and 37 t forklifts
  • Machine setting, levelling and anchoring across every line
  • 480 V power distribution and machine connections
  • Compressed air, process water and coolant piping
  • Connection-point validation and documented hand-over
  • Work performed inside a live production plant